Clark Ave School getting Ready for Special Opening

The opening of the fully-completed Clark Avenue Middle School is just about one month away, and work crews are finishing up the final preparations to welcome students into the completed new school project – after more than three years and two phases of construction.

“I think we’re shooting for substantial completion by the middle of August,” said Gerry McCue of the Chelsea Schools. “Teachers go back on Aug. 27 and students come into the new school on Aug. 29. We expect to have the school operational then. There will be punch list items to get to, but nothing major will be left.”

The completion of Phase 2 will mark the end of the $57 million project that started under former City Manager Jay Ash, and was carried out by City Manager Tom Ambrosino and the School Department.

Already, Phase 1 opened in December 2017, and students and teachers have been using half of the school since that time. The former building, the Old Chelsea High, had been completely demolished earlier this year to make way for Phase 2.

Demolition of the other side of the old high school started in March 2015, when the project first got off the ground.

With the addition of the Phase 2 building, the school will be introduced to many of the amenities, including the gym, an auditorium, a small performance stage, the library, technology labs, art rooms, music rooms, an administrative suite and the new front courtyard facing Crescent and Clark Avenues.

“In addition to things like the gym, there will be a smaller performance space and things can be done on that stage and the cafeteria can be used for seating,” he said. “Larger productions can be done in the auditorium. That’s important because the Clark Ave is the feeder program for the Chelsea High Drama Club, so they have an emphasis on music and performing arts at the Clark Avenue.”

The courtyard will be a very welcome addition to the school and the neighborhood, he said. The space was designed to open up to Crescent and Clark Avenues so that the buildings are pushed back and the space seem more open and inviting. He said the possibilities are endless for the new space.

“We could do outdoor performances or in the summer the City could have a movie night for the neighborhood out there,” he said. “There will be seating and decking in the courtyard. There will also be a school garden there too. There has been a big emphasis on school gardens across the district and the Clark Ave will have one too.”

He said that the top floors are pretty much completed, and many classrooms are set up now. He said the bottom floor is still having work done – as the contractor started from the top and worked down.

As it is, the action is aplenty on the site as the final work is completed.

“There’s just a lot of activity there now and it will be non-stop until the first day of school,” he said.

The Clark Avenue School is expected to have 668 students when it opens in August.