Island End River in the Midst of Major Flood Protection Project

Few places in the food supply chain for Greater Boston and beyond are more vulnerable than the New England Produce Center.

That huge food resource for the region, along with other industries, are very close to sea level and, as discovered a few years ago, very prone to flooding and sea level surges.

Now, the City of Chelsea is poised to begin a major project at the Island End River that will help to protect the industrial areas along Beacham Street and enhance the environment around the improving Island End River.

“That area is about six or seven feet above sea level now, and experts expect sea level and storm surges at 14 feet above sea level by the end of the century,” said Alex Train, of the Chelsea Planning Department. “This project is in concert with Everett and it’s gathered a lot of momentum. It’s a priority of the City Manager and our department because we understand how much is at risk. It’s a gamble otherwise and we don’t like to gamble in the planning industry.”

Such a gamble was clearly seen two winters ago when huge coastal surge storms lifted the water levels into the industrial areas along the Island End, nearly causing major disruptions and opening a lot of eyes to the vulnerability of the situation.

The project has been supported by a grant from the Coastal Zone Management Office, as well as the Chelsea and Everett City Councils.

The project includes gray infrastructure, such as flood walls and berms by the Island End River. It also includes green infrastructure with the restoration of the salt marshes abutting the Island End. At the same time, they will also be able to add some amenities for the public like a Boardwalk to connect to the Admiral’s Hill Marina area.

“It’s going to be a sizeable project, but in the context of the surrounding industrial businesses and the produce center, it’s easily a worthwhile initiative on our end,” said Train.

Right now, in Chelsea, they are at 60 percent engineering design on the project. Everett is a little bit further behind as they are in the Designated Port Area (DPA) and require many more steps. Everett is currently in a schematic design phase.

On the Chelsea side, Train said they will culminate design this summer, and then look for further grants this winter. Then they will engage in the final engineering, permitting and construction phases.

The project will also be tied into the large Beacham Street roadway, sidewalk and bike path improvements that are also coming soon.

A report in 2015 by the Metropolitan Area Planning Council (MAPC) showed that the Produce Center generates $2.3 billion of economic activity per year, and the entire industrial district generates $7 billion per year. There are 5,000 direct jobs there and 10,000 supportive jobs there.

“Many of that activity and those jobs benefit Chelsea and Everett residents and they are solid middle-class jobs and we’re committed to protecting them for our residents,” said Train.

Other Development Activity

•The City has received a PARC grant for rehabilitation of the O’Neil Playground on the hill up from Williams Street. The new design will encourage water features and tree canopies. The restoration will look to prevent heat islands and provide a cool place during the summer. The project is currently under construction and should be substantially completed by the fall. It came in at a cost of $884,000.

•The Eden Street playground is currently in design. The new design will also feature a robust tree canopy and more permeable surfaces. The project will be bid out in September, with a fall start. Construction will start up again in the spring for a substantial completion by summer 2020. That project was supported by a $400,000 PARC grant.

•Voke Park is another area that will soon receive more attention. The Bocce Court and fields were done over two years ago, but now it’s time for some attention to be paid to the playground. Already, they have had one public meeting to get input on the park, and they are working on conceptual designs now.

“We’ll apply for a grant in July to secure funding,” said Train.

Design will be done in June 2020 and construction on that is likely to be 2021.

•The City is preparing to modernize the traffic signals and intersections at Williams/Chestnut and Williams/Broadway this summer. That upgrade will include new Smart Traffic Signals that are able to read the traffic flow and adjust signal timing on the fly. One of those lights has already been installed on Broadway and Webster earlier this year. Sidewalks will also be touched up as well.