Decision on Two-Way Broadway Traffic Draws Differing Opinions

The good news for Chelsea residents is that the $5 million redesign of the Broadway business district is moving forward, and a final decision will be made by the City Council about its exact components next month.

And if the vision and innovativeness that City Manager Tom Ambrosino fostered in all parts of Revere can be matched here, then Chelsea residents can expect a Broadway and Bellingham Square bustling with activity and commerce.

But a big question about “The New Broadway” remains: Should the six city blocks from Williams Street to City Hall Avenue be a one-way street (as it exists now and has for many decades) or a two-way street?

The Chelsea Traffic Commission hosted a public meeting Tuesday night at City Hall to hear residents’ opinions about the potential change of Broadway to a two-way street. The Commission is scheduled to vote on the matter at its next meeting before the Council casts the final vote about the entire redesign project, including the traffic plan.

Alexander Train, Chelsea’s assistant director of the department of planning and development, gave a thorough presentation of the re-imagined Broadway project that will totally transform the business district’s intersections, sidewalks, bicycle paths, tree pits, and physical appearance.

“We’ve completed the planning and development portion of the process and we’re now approaching the Traffic Commission to vote and adopt and enact the plan,” said Train. “Their vote will be relayed to City Council, who has the authority to approve or reject their decision.”

Police Chief Brian Kyes spoke in favor of a two-way Broadway, saying it would improve the flow of traffic.

“If a person double parks his vehicle, we have a reason to tow the vehicle ASAP,” said Kyes. “We want to keep the traffic flowing.”

Kyes said he was happy to hear that the intersection of Broadway and Third Street will have traffic lights in the redesign project. “Broadway and Third is probably one of the most dangerous intersections in the entire state,” said Kyes.

He said that when he drove from the police station to City Hall for the meeting, “the backup when I got to Hawthorne Street was incredible, because everybody is making the loop (around Broadway). I think the final [redesign] project makes a lot of sense. I drive down Broadway, Revere all the time and I very, very rarely see double parking there.” Councillor-at-Large Damlili

Vidot said she would like to see the city pay more attention to cleaning up Broadway (such as removing the weed in the metal grates). She also disputed the claim that two-way traffic would curtail double parking and that it would make it safer for pedestrians. She also asked about potential back-ups on the Tobin Bridge and how it would affect traffic on a two-way Broadway.

Vidot said she was not happy with the swiftness of the entire redesign process.

“I urge everyone to just take several steps back and let’s figure out a way to engage more people,” said Vidot. “The way that this process has gone, having a meeting in the middle of summer when the City Council isn’t even meeting – in a hot room where everyone is aggravated and we had to wait 10 minutes to even start the meeting, all of it is just not right.”

Ambrosino, who favors a two-way Broadway, said the traffic configuration should not predominate the discussion of the redesign project.

“That’s only a small part of the reimaging Broadway,” said Ambrosino. “Many of the improvements [to Bellingham Square, Fay Square, City Hall Avenue, traffic signals at dangerous intersections] are happening regardless of which of these two configurations between Williams and Fifth Streets is chosen. Even the one-way configuration is a major improvement over the two-lane speedway that currently exists on Broadway. The two-way configuration is still safer, calmer, and slower for bicylists and pedestrians.”

Ambrosino said the two-way configuration will be “transformative.”

“It will make a difference to the feel and the look of that downtown. It makes it vibrant. It makes it aesthetically pleasing. This will be better for pedestrians, for traffic, and for businesses.”

Rick Gordon, owner of Allen Cut Rite on Broadway, said the No. 1 issue in the downtown district is parking. “I personally prefer a one-way plan for the flow of traffic. The street is much narrower than other communities and I don’t think two-way makes a business more visible.”

Gordon credited the Chelsea Police for their efforts in slowing down motorists and enforcing double-parking restrictions on Broadway. Some residents at the meeting had noted that double-parking is a recurring issue on Broadway.

 

 

 

Councillor-at-Large Roy Avellaneda, whose family owns Tito’s Bakery, asked whether the City Council will have to vote on the redesign project in its entirety as opposed to voting on individual components such as the traffic configuration, and the placement of new bus stops and traffic lights on Broadway.

Following more than two hours of discussion, the one-way/two-way Broadway issue remains a hotly debated one and all eyes will be on the Traffic Commission when it convenes for a vote at its next meeting.WE should be Ambrosino said he favors a two-way Broadway