Mystic/Tobin’s Everett Avenue Onramp to Close May 7 for One Month

The state Department of Transportation (MassDOT) announced several changes to the Mystic/Tobin Bridge repair project, including the one-month closure of the Everett Avenue on-ramp May 7.

MassDOT announced that since several projects in the area are coming underway – including the Alford Street Bridge, the North Washington Street Bridge, and Commonwealth Avenue Bridge in Boston – they have adjusted the Tobin work to not close a lane permanently on the lower deck northbound.

This schedule adjustment means that MassDOT will no longer be implementing a permanent lane closure on the lower deck (Route 1 northbound) from April 22 through November of this year but will instead be adjusting the width of the travel lanes in this area and utilizing off-peak lane closures. Three full lanes of travel will be in place on the bridge this year during peak commute hours.

The full list of impacts this construction season is now as follows:

  • Temporary off-peak lane closures on the lower deck (Route 1 northbound) from now through November 2018.
  • Temporary off-peak lane closures on the upper deck (Route 1 southbound) from now through November 2018.
  • Everett Avenue on-ramp closed at all times for one-month period beginning on May 7.
  • Beacon Street off-ramp closed at all times for a two-month period beginning in summer 2018.
  • Fourth Street off-ramp closed for a one-month period in 2019.

No more than one ramp will be closed at any given time throughout the duration of the project.

“We are investing historic levels of funding into our highway transportation system and we are seeking to do so in ways that minimize impacts on the travel public and our local communities,” said Highway Administrator Jonathan Gulliver. “Our construction teams have worked hard to optimize the schedule of operations to better accommodate travel throughout this area. We continue to encourage members of the public to learn about upcoming traffic impacts and use the appropriate tools to make the best decisions on traveling in order to reach their destinations in an efficient manner.”

This $41.6 million maintenance project involves repairing a section of the deck of the Tobin Bridge which carries traffic between the Charlestown neighborhood of Boston and Chelsea. Work is scheduled to be completed at the end of 2020 with lane closures and traffic impacts occurring during each of the 2018, 2019, and 2020 construction seasons.

Work will include steel repairs to the upper and lower decks, concrete deck work on the lower deck, followed by waterproofing, resurfacing, and installing pavement markings. Operations will also consist of utility installation, installing curbing, paving, constructing a new parking lot under the bridge between Williams Street and Third Street.