Silver Line Stations Come Together, Service to Begin in April 2018

By Seth Daniel

The new Chelsea Station behind the Market Basket on Everett Avenue is nearly completed now, with a goal of opening up service at the four new stations on the new SL3 line in April.

The new Chelsea Station behind the Market Basket on Everett Avenue is nearly completed now, with a goal of opening up service at the four new stations on the new SL3 line in April.

A projected 19 minute ride with no transfers from downtown Chelsea to the Seaport in Boston is but months away as the MBTA puts the finishing touches on four stations and the dedicated busway in Chelsea’s new Silver Line Bus Rapid Transit (BRT) line – which will be known as SL3.

Already, a great amount of excitement has built throughout the community as the stations begin to look like finished products and the lettering denoting ‘Eastern Avenue’ and ‘Chelsea’ have been affixed to those stations. A spokesman for the MBTA said the T is excited to start service in April.

“The MBTA and MassDOT are very excited to be just months away from introducing Bur Rapid Transit service for customers traveling to and from Chelsea,” said Joe Pesaturo, for the MBTA. “The MBTA anticipates beginning Silver Line Gateway service in the early spring of next year. The existing Silver Line in Boston has been very popular since its launch because of the frequent levels of service and increased capacity. MBTA General Manager Luis Ramirez is looking forward to a celebration in the spring in Chelsea to mark the start of service.”

The completion of the four new BRT stations and the dedicated busway will conclude Phase 1 of the Silver Line Gateway expansion project – which has essentially brought the Silver Line from Logan Airport over to Chelsea. The new Chelsea service, however, will not go to the airport and the SL3 line will bypass the airport with a stop at the Blue Line Train Station where airport shuttles can be taken to terminals.

In documents presented to the MBTA Board last summer, the new service expects to have a total daily ridership of 8,730 people, with new transit trips being 2,500 (meaning people that will use the service who now do not use the MBTA).

At peak, it is estimated there will be 22 BRT buses on all three Silver Line routes, and that the SL3 Chelsea wait times will be around 10-12 minutes at peak times and 12-15 minutes at off-peak times.

MBTA estimates show that currently to get to the World Trade Center stop in the Seaport from downtown Chelsea takes 37 minutes and requires two transfers. That would be paired down to 19 minutes and no transfers on the new SL3 line.

To go from the airport to the World Trade Center station now takes 20 minutes with one transfer. The SL3 line would take seven minutes and no transfers.

The entire first phase of the Silver Line Gateway project cost $46.5 million and included rebuilding the Washington Avenue bridge, constructing a 1.1 mile dedicated busway, a half-mile shared-use path and the four new stations.

A second phase has been fully funded at about $29 million and includes building the Chelsea Intermodal Center, which includes a new Commuter Rail Station and a new railroad signaling system to improve traffic flow in Chelsea. The new station, unlike the existing station, will be fully accessible. The MBTA expects to solicit construction bids for Phase 2 this winter, with work beginning next summer.

One of the key initiatives for MBTA General Manager Ramirez, he said, is to get a comprehensive strategy for marketing a promoting the new service well in advance of the launch. Many of the new service options introduced by the MBTA in recent years suffer from low ridership due in many cases to people having little information about the new service.

The MBTA right now is working to select a qualified firm to handle the jobs of:

•Advertise the new service to existing and prospective customers.

•Highlight the benefits of Silver Line Gateway service relative to existing bus services in the area, including dedicated lanes and limited stops.

•Promote the ongoing work the MBTA is doing to improve its transportation offerings.

“The firm will work with the MBTA to develop well-rounded marketing and communications strategies that achieve the goals, including but not limited to market research, specifying target audiences, generating message concepts, proposing an effective mix of media, and partnering with local community organizations as part of the public outreach strategy,” said Pesaturo.

 